a contactor hired 150 men to pave a road in 30 days.how many mem will be hire to do the same work in 20 days​

Respuesta :

kevinmario2008 kevinmario2008
  • 05-12-2021

Answer:375

Step-by-step explanation:W = RTN

1 = 1/7500(20)N

1 = 20/7500N

1 = 2/750N

750(1 = 2/750N)

750 = 2N

750/2 = N

375 = N

There are 375 men to do the job in 20 days

Answer Link

Otras preguntas

A box of nutmeg weighs 99.66 grams. If there are 22 teaspoons of nutmeg in the box, how much does one teaspoon of nutmeg weigh? (Round your answer to the neares
Generally speaking, using a ______ year's history of cash receipts and disbursements will be a satisfactory basis for projecting the future. Part of a year or
In what ways can you respond to God’s love?
Which of the following are skills? Select all that apply. -typing -talking -critical thinking -playing pool
If 100C2 has a value of 4,950, what is the value of 100C98? A. 4,950 B. 99,000 C. 49,500 D. 9,900
Which of the following strategies is part of a pre-reading plan? (5 points) prepare postpone part plan
Simplify: (15-6)^2-34/2 Please show strategies.
Which term refers to the accuracy of the health record?
A marble is drawn at random from the bag shown below. The bag contains 3 green, 4 yellow, 5 blue, and 8 pink marbles.What is P(not pink)?
Alan had 2 mirrors installed in his house.The first mirror was 2 yards and 2 3rds yards wide the second mirror was 2 yards tall and 3 2 halfs wide. Is the area