12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

true or false one milliliter of water has a mass of 2.00 grams​
The diameter of the base of the cone measures 8 units. The height measures 6 units. What is the volume of the cone? A)240 cubic units B)321 cubic units C)48X cu
How did Columbus react after he reached Hispaniola on his second voyage and found that his men had been killed by American Indians?
A sales representative from a local radio station is trying to convince the owner of a small fitness club to advertise on her station. The representative says t
Which of the following is accurate regarding both West Africa and Latin America before 1500?
The atomic number of an element is found by?
All states have a state tax.
Multiply3x^2(4x^2+ 6x – 3)A 7x^2 + 92 – 6B 12x4 +180 - 9C 12x^2 + 182 – 9D 12x^4 + 18x3 - 9x^2​
Which of the following will most likely result from having a healthy state of mental well-being? A. More powerful muscles B. More attractive friends C. More anx
Bias by omission includes which of the following?