When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

Tina conducted an experiment to test her hypothesis. Her hypothesis was that by crushing aspirin and putting it into potting soil increases the growth rate of t
Which body of water is to the east of Central America?
Most American citizens must pay taxes. true or false?
Which of the following is not part of the drafting process? Focus on spelling conventions Gather ideas Refine voice Work on word choice
is -12 colder than -2
Odysseus spends a lot of time talking about the very strong wine that Maron gave him. What kind of literary device is this? epic simile foreshadowing extended
A sentence that contains both dependent and independent clauses is known as a
why would someone want a midwife to deliver their baby?
What is the worst school in the U.S
on June 1, 2013, the number of hours of daylight in Anchorage, Alaska was 18 1/4 hours. what was the number of hours without daylight?