a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

The two most abundant elements in ocean water, besides hydrogen and oxygen, are A) salt and sodium. B) salt and chlorine. C) sodium and calcium. D
divide. draw a number line or use fraction strips. 3÷1/2=
write a real world problem that could be represented by d-32=64
two problems that led to romes decline
To increase the brightness of a desk lamp, a student replaces a 50-watt incandescent lightbulb with a 100-watt incandescent lightbulb. Compared to the 50-watt l
By 1860 where were most of the country's goods manufactured
why are large astronomy whole body such as planets and stars round
Why were there no cables for electricity in the early elevators
How many electrons are in the outermost energy shell of a calcium atom?
If you cut a flatworm in half, both halves can grow into a new individual by _____. budding fission fragmentation